Closed
This road needs a 40 mph sign replacing
Reported via desktop in the Sign (unlit) category anonymously at 11:37, Thu 19 November 2020
Sent to Lincolnshire County Council less than a minute later. Council ref: 380203.
This road is in a poor state caused by subsidence and has previously had a 40 mph speed limit applied to it which appears to have been removed. With winter and bad weather coming unless the road is repaired it is dangerous to travel at the speed some cars do
Updates
-
Thank you for your report. We will investigate and make an update to this report within 14 days.
Posted by Lincolnshire County Council at 11:37, Thu 19 November 2020
-
What is the update in this? Apparently there was another accident here last week with an response from the emergency services.
Posted anonymously at 11:48, Tue 22 December 2020
-
This report has been assessed and works are planned. We will update this report when works are scheduled.
State changed to: In progress
Posted by Lincolnshire County Council at 15:03, Tue 22 December 2020
-
State changed to: Investigating
Updated by Lincolnshire County Council at 15:14, Wed 6 January 2021
-
This report has been assessed and works are planned. We will update this report when works are scheduled.
State changed to: In progress
Posted by Lincolnshire County Council at 15:20, Wed 6 January 2021
-
Whilst works are being planned is it possible to have a temporary speed limit sign please.
Posted anonymously at 09:15, Mon 1 February 2021
-
State changed to: Investigating
Updated by Lincolnshire County Council at 16:17, Wed 3 February 2021
-
We acknowledge your concerns and accept that the highway has deteriorated in condition. We have assessed the fault in accordance with our Highways Infrastructure Asset Management Plan and it does not require urgent action. If the fault deteriorates significantly please report this again to us. Thank you for reporting this matter.
State changed to: No further action
Posted by Lincolnshire County Council at 13:20, Tue 9 February 2021
-
State changed to: Investigating
Updated by Lincolnshire County Council at 13:18, Fri 12 February 2021
-
It is our intention to reconstruct the section from Digby Dam to Dorrington Fen Road using recycling techniques. The works programme has yet to be finalized and will be dependent on Specialist Sub contractors availability but it is hoped to carry out the works within the autumn period of 2021. It is anticipated that the works will take approximately 14 days to complete. Thank you for reporting this matter.
State changed to: No further action
Posted by Lincolnshire County Council at 09:03, Wed 3 March 2021
This report is now closed to updates from the public. You can make a new report in the same location.