Sewage tankers have destroyed the road
Reported via mobile in the Damaged road edge, encroaches more than 100mm category anonymously at 17:12, Sun 22 May 2022
Sent to Lincolnshire County Council less than a minute later. Council ref: 424806.
The damage is colossal it extends way past the picture taken. The road and associated bank seems to be slipping into the canal after the relentless abuse given to it by tankers visiting the sewage works 24/7! If the canal water level rises there will be a flood!!!
Updates
-
Thank you for your report. We will investigate and make an update to this report within 14 days.
Posted by Lincolnshire County Council at 17:12, Sun 22 May 2022
-
We need to investigate this report. We will contact you again when an update is available.
State changed to: Investigating
Posted by Lincolnshire County Council at 16:35, Fri 27 May 2022
-
This report has been assessed and works are planned. We will update this report when works are scheduled.
State changed to: In progress
Posted by Lincolnshire County Council at 09:26, Mon 13 June 2022
-
We have an update. Our highways team have issued this work out to one of their delivery gangs. We’ll let you know when the job is complete.
State changed to: Action scheduled
Posted by Lincolnshire County Council at 13:34, Mon 5 September 2022
-
Great news, we’ve had a look at the issue and we have now passed to our Highways Officers for the team to assess what can be done to resolve the matter. We’ll let you know when the assessment has taken place.
State changed to: Investigating
Posted by Lincolnshire County Council at 14:05, Mon 7 August 2023
-
Progress! We’ve completed our investigation and works are now planned. Once we know when work is due to take place we will let you know.
State changed to: In progress
Posted by Lincolnshire County Council at 08:47, Mon 2 October 2023
-
State changed to: Investigating
Updated by Lincolnshire County Council at 11:44, Thu 28 December 2023
-
We are sorry but we are not taking immediate action with this report however work to patch and reconstruct the road at the location described is being considered, however we are currently unable to provide timescales for this. Thank you for reporting this matter.
State changed to: No further action
Posted by Lincolnshire County Council at 10:57, Wednesday 3 January 2024
-
We have an update. Our highways team have issued this work out to one of their delivery gangs. We’ll let you know when the job is complete.
State changed to: Action scheduled
Posted by Lincolnshire County Council at 17:04, Monday 8 January 2024
-
State changed to: In progress
Updated by Lincolnshire County Council at 08:35, Monday 19 February 2024
-
All done! The work’s finished and the issue is now resolved. Thank you for contacting us about this. Your report has meant that we can focus our effort where it’s needed most.
State changed to: Fixed
Posted by Lincolnshire County Council at 17:49, Monday 19 February 2024