In progress
Bollard knocked down
Reported via mobile in the Bollards (lit) category by South Holland Community Action Group at 11:37, Sun 26 June 2022
Sent to Lincolnshire County Council less than a minute later. Council ref: 426772.
The top covered of the lit bollard here has been hit and is loose on the carriageway. Please arrange for contractors to secure and reattach.
Updates
-
Thank you for your report. We will investigate and make an update to this report within 14 days.
Posted by Lincolnshire County Council at 11:37, Sun 26 June 2022
-
Thank you for your report. We will investigate and make an update to this report within 14 days.
Posted by Lincolnshire County Council at 12:05, Sun 26 June 2022
-
This report has been assessed and works are planned. We will update this report when works are scheduled.
State changed to: In progress
Posted by Lincolnshire County Council at 12:05, Sun 26 June 2022
-
Works are scheduled.
State changed to: Action scheduled
Posted by Lincolnshire County Council at 12:05, Sun 26 June 2022
-
State changed to: In progress
Updated by Lincolnshire County Council at 12:35, Sun 26 June 2022
-
We're sorry, but after visiting site we were unable to resolve the issue immediately and further works are required. Thank you for your patience, we will contact you again when a further update is available.
Posted by Lincolnshire County Council at 15:01, Sun 26 June 2022
-
This report has been assessed and works are planned. We will update this report when works are scheduled.
Posted by Lincolnshire County Council at 07:44, Mon 27 June 2022