In progress
94-98 Broadgate Lane
Reported via desktop in the Standing water covering less than half the road category anonymously at 13:38, Tue 1 November 2022
Sent to Lincolnshire County Council less than a minute later. Council ref: 435439.
Ongoing issue. During periods of both heavy and light rainfall surface water ponding occurs along Broadgate Lane from its junction with Spalding Road. The standing water restricts the use of the footpath by pedestrians fronting properties 94-98 Broadgate Lane. A NEW ROAD GULLY SHOULD BE INSTALLED TO PREVENT THIS FLOODING ISSUE. The ponding has also become worse since the carriageway was resurfaced by LCC during Spring 2022.
Updates
-
Thanks for letting us know about your issue with standing water covering less than half the road. We will look into this and let you know what we find within the next 14 days. You can find out more about flooding and drainage on our website
Posted by Lincolnshire County Council at 13:38, Tue 1 November 2022
-
Great news, we’ve had a look at the issue and we have now passed to our Highways Officers for the team to assess what can be done to resolve the matter. We’ll let you know when the assessment has taken place.
State changed to: Investigating
Posted by Lincolnshire County Council at 09:00, Wed 2 November 2022
-
Just to let you know this issue has turned out to be more complicated than we first thought. We need to take this on for more investigation. We will let you know the situation as soon as we can. Thanks for bearing with us.
Posted by Lincolnshire County Council at 11:16, Mon 28 November 2022
-
Progress! We’ve completed our investigation and works are now planned. Once we know when work is due to take place we will let you know.
State changed to: In progress
Posted by Lincolnshire County Council at 12:57, Thu 1 December 2022
-
Great news, we’ve had a look at the issue and we have now passed to our Highways Officers for the team to assess what can be done to resolve the matter. We’ll let you know when the assessment has taken place.
State changed to: Investigating
Posted by Lincolnshire County Council at 12:59, Thu 1 December 2022
-
Progress! We’ve completed our investigation and works are now planned. Once we know when work is due to take place we will let you know.
State changed to: In progress
Posted by Lincolnshire County Council at 13:16, Thu 1 December 2022
-
We have an update. Our highways team have issued this work out to one of their delivery gangs. We’ll let you know when the job is complete.
State changed to: Action scheduled
Posted by Lincolnshire County Council at 14:05, Wed 28 December 2022
-
Photo taken within the past 2 weeks. Any progress on the completion of the job following your update of the 28 Dec 2022?
Posted anonymously at 15:47, Friday 28 April 2023
-
Any update please? The flooding on the footway remains an issue for pedestrians.
Posted anonymously at 18:22, Friday 21 July 2023
Provide an update
Your information will only be used in accordance with our privacy policy