Beaufort St, Gainsborough DN21 2RT
Reported via Android in the Pothole on road/cycleway category by David gibson at 15:04, Tuesday 2 April 2024
Sent to Lincolnshire County Council less than a minute later. Council ref: 2801717.
Beaufort St, Gainsborough DN21 2RT.
Along the road you have around 7 potholes various sizes some large and some not as big but all deteriorating and getting bigger by the day with each vehicle.
Around 7 main ones and lots of small ones.
I kindly request that they all get cleaned out and fixed properly .
Updates
-
Thanks for letting us know about your issue with a pothole on the road or cycleway. We will look into this and let you know what we find within the next 14 days. You can find out more about potholes on our website
Posted by Lincolnshire County Council at 15:04, Tuesday 2 April 2024
-
Progress! We’ve completed our investigation and works are now planned. Once we know when work is due to take place we will let you know.
State changed to: In progress
Posted by Lincolnshire County Council at 09:29, Wednesday 3 April 2024
-
We have an update. Our highways team have issued this work out to one of their delivery gangs. We’ll let you know when the job is complete.
State changed to: Action scheduled
Posted by Lincolnshire County Council at 09:29, Wednesday 3 April 2024
-
Any have sent a man out who painted yellow around them but not yet been repaired
Posted by D gibson at 16:54, Sunday 7 April 2024
-
Still not fixed
Posted by D Gibson at 22:43, Monday 6 May 2024
-
Still not been fixed just getting bigger 😒
Posted by D Gibson at 14:40, Wednesday 29 May 2024
-
State changed to: In progress
Updated by Lincolnshire County Council at 13:18, Thursday 30 May 2024
-
All done! The work’s finished and the issue is now resolved. Thank you for contacting us about this. Your report has meant that we can focus our effort where it’s needed most.
State changed to: Fixed
Posted by Lincolnshire County Council at 14:28, Thursday 30 May 2024
-
Updated by Lincolnshire County Council at 08:57, Friday 31 May 2024
-
Come on council you have marked them for repair just send the ppl out and repair all of them spend them for the 1 day too sort all of them out and the cracks .
This is a dead end road so if redone it shouldn't need doing again .
Fix are steet