The camber of this part of Tetney Lock Road is very dangerous as it drops away on both sides of the road quite steeply at various locations of both sides of the road up to the Hoop End turn off. This issue is getting progressively worse.
Updates
-
Thanks for letting us know about your issue with a pothole on the road or cycleway. We will look into this and let you know what we find within the next 14 days. You can find out more about potholes on our website
Posted by Lincolnshire County Council at 20:55, Thu 18 April 2024
-
Great news, we’ve had a look at the issue and we have now passed to our Highways Officers for the team to assess what can be done to resolve the matter. We’ll let you know when the assessment has taken place.
State changed to: Investigating
Posted by Lincolnshire County Council at 09:35, Fri 19 April 2024
-
Just to let you know this issue has turned out to be more complicated than we first thought. We need to take this on for more investigation. We will let you know the situation as soon as we can. Thanks for bearing with us.
Posted by Lincolnshire County Council at 11:49, Fri 19 April 2024
-
Progress! We’ve completed our investigation and works are now planned. Once we know when work is due to take place we will let you know.
State changed to: In progress
Posted by Lincolnshire County Council at 14:46, Thu 23 May 2024
-
This is still getting progressively worse - with 50cm drops now in places. Also cracking of the road in various places from the Oil Terminal To Tetney Lock itself now. This is fast becoming a very dangerous road to Tetney, which has sadly already resulted in 2 fatalities.
Posted anonymously at 15:16, Thu 15 August 2024
-
We have an update. Our highways team have issued this work out to one of their delivery gangs. We’ll let you know when the job is complete.
State changed to: Action scheduled
Posted by Lincolnshire County Council at 16:25, Mon 28 October 2024
-
State changed to: In progress
Updated by Lincolnshire County Council at 07:44, Monday 10 March 2025
-
All done! The work’s finished and the issue is now resolved. Thank you for contacting us about this. Your report has meant that we can focus our effort where it’s needed most.
State changed to: Fixed
Posted by Lincolnshire County Council at 13:46, Wednesday 12 March 2025
This report is now closed to updates from the public. You can make a new report in the same location.