Action scheduled
Multiple pathway ossues
Reported via iOS in the Trip hazard/uneven surface category anonymously at 19:45, Saturday 25 May 2024
Sent to Lincolnshire County Council less than a minute later. Council ref: 2807515.
In the photos of she of path , middle of pathway cracked , missing damaged and uneven!
Updates
-
Thanks for letting us know about your issue with a trip hazard or uneven surface. We will look into this and let you know what we find within the next 14 days. You can find out more about pavement maintenance on our website
Posted by Lincolnshire County Council at 19:45, Saturday 25 May 2024
-
Great news, we’ve had a look at the issue and we have now passed to our Highways Officers for the team to assess what can be done to resolve the matter. We’ll let you know when the assessment has taken place.
State changed to: Investigating
Posted by Lincolnshire County Council at 07:49, Thursday 30 May 2024
-
Just to let you know this issue has turned out to be more complicated than we first thought. We need to take this on for more investigation. We will let you know the situation as soon as we can. Thanks for bearing with us.
Posted by Lincolnshire County Council at 14:42, Thursday 30 May 2024
-
We have an update. Our highways team have issued this work out to one of their delivery gangs. We’ll let you know when the job is complete.
State changed to: Action scheduled
Posted by Lincolnshire County Council at 14:59, Thursday 30 May 2024
-
Great news, we’ve had a look at the issue and we have now passed to our Highways Officers for the team to assess what can be done to resolve the matter. We’ll let you know when the assessment has taken place.
State changed to: Investigating
Posted by Lincolnshire County Council at 07:50, Monday 15 July 2024
-
Just to let you know this issue has turned out to be more complicated than we first thought. We need to take this on for more investigation. We will let you know the situation as soon as we can. Thanks for bearing with us.
Posted by Lincolnshire County Council at 10:56, Monday 15 July 2024
-
Progress! We’ve completed our investigation and works are now planned. Once we know when work is due to take place we will let you know.
State changed to: In progress
Posted by Lincolnshire County Council at 15:28, Monday 15 July 2024
-
We have an update. Our highways team have issued this work out to one of their delivery gangs. We’ll let you know when the job is complete.
State changed to: Action scheduled
Posted by Lincolnshire County Council at 14:08, Monday 7 October 2024
Provide an update
Your information will only be used in accordance with our privacy policy