Fixed
Under bridge, recent repairs disintegrated, standing water still apparent.
Reported via mobile in the Pothole on road/cycleway category anonymously at 20:54, Tuesday 14 January 2025
Sent to Lincolnshire County Council less than a minute later. Council ref: 2830166.
Full width of road, recent repairs deteriorated, local traffic slowing to cross centre of road in turn.
Updates
-
Thanks for letting us know about your issue with a pothole on the road or cycleway. We will look into this and let you know what we find within the next 14 days. You can find out more about potholes on our website
Posted by Lincolnshire County Council at 20:54, Tuesday 14 January 2025
-
Great news, we’ve had a look at the issue and we have now passed to our Highways Officers for the team to assess what can be done to resolve the matter. We’ll let you know when the assessment has taken place.
State changed to: Investigating
Posted by Lincolnshire County Council at 07:37, Wednesday 15 January 2025
-
Progress! We’ve completed our investigation and works are now planned. Once we know when work is due to take place we will let you know.
State changed to: In progress
Posted by Lincolnshire County Council at 09:06, Wednesday 15 January 2025
-
This is seriously urgent. As you go under the bridge West to East you cannot see if there is oncoming traffic due to the bridge structure. Traffic going in both directions veers over to avoid the potholes. There is a realistic possibility of head on collision.
Posted anonymously at 11:31, Wednesday 15 January 2025
-
We have an update. Our highways team have issued this work out to one of their delivery gangs. We’ll let you know when the job is complete.
State changed to: Action scheduled
Posted by Lincolnshire County Council at 11:39, Thursday 30 January 2025
-
This area has been an issue for over a year now. There are numerous holes and serious flooding. The repairs being carried out are poor quality and at best last a few days. The holes cannot be avoided and you need to position your vehicle to the centre of the road with blind bends either side of the bridge. It would even be helpful if warning signs were put in place. I expect numerous vehicles have been damaged, mine has. It is only a matter of time before there is a serious accident here.
Posted anonymously at 14:27, Tuesday 4 February 2025
-
There appeared to have been some repair to this ongoing problem a week ago. But now the road surface is as bad as ever. Proper lasting repairs are needed here
Posted anonymously at 08:04, Tuesday 11 February 2025
-
State changed to: In progress
Updated by Lincolnshire County Council at 08:40, Wednesday 5 March 2025
-
All done! The work’s finished and the issue is now resolved. Thank you for contacting us about this. Your report has meant that we can focus our effort where it’s needed most.
State changed to: Fixed
Posted by Lincolnshire County Council at 13:05, Thursday 6 March 2025
Provide an update