Action scheduled
Trip hazard/uneven surface problem
Reported in the Trip hazard/uneven surface category anonymously at 13:41, Fri 28 February 2025
Council ref: 4201774.
Dangerously loose footpath.
Updates
-
Thanks for letting us know about your issue with a trip hazard or uneven surface. We will look into this and let you know what we find within the next 14 days. You can find out more about pavement maintenance on our website
Posted by Lincolnshire County Council at 15:32, Fri 28 February 2025
-
We have an update. Our highways team have issued this work out to one of their delivery gangs. We’ll let you know when the job is complete.
State changed to: Action scheduled
Posted by Lincolnshire County Council at 11:46, Mon 3 March 2025
-
One Network stated on the 1st June that permission had been granted to conduct roadworks to fix the broken path in South Street the 14th of July. On 1st July LCC published a temporary traffic regulation Order for Cross Street/South Street stating that Footway patch & reconstruction would take place between the 14/07/2025 - 17/07/2025. This does not appear to have happened but I now see that a large part of Gainsborough is having their footpaths repaired whilst Morton waits until hell freezes over for ours to be brought to a respectable standard. Please can you state why this job has not been completed.
Posted by Cllr Bruce Allison at 10:08, Wed 23 July 2025
-
The pavement has still not been repaired even though it was meant to start on the 14th of July. It is extremely dangerous for the elderly people who live here.
Posted anonymously at 11:44, Mon 4 August 2025
Provide an update