In progress
Under railway bridge - 15/01/26
Reported via mobile in the Standing water covering more than half the road category anonymously at 21:40, Thursday 15 January 2026
Sent to Lincolnshire County Council less than a minute later. Council ref: 2869804.
Continuation of issue raised council refs: 2861162 (12/11/25) and 2865788 (16/12/25). Water is still not draining away under bridge on busy A151. This is the third month running. Please note this is on a blind bend and causes cars to use middle of road to cross. LCC attended too late to see the problem last month so no action was taken. The solution previous to last month was the use of warning triangles, however they are placed in a verge so obscured and also far enough away from hazard that cars are able to react in good time. Ongoing issue that is not being addressed by the responsible party resulting in liability of major and ongoing hazard to road users.
Updates
-
Thanks for letting us know about your issue with standing water covering more than half the road. We will look into this and let you know what we find within the next 14 days. You can find out more about flooding and drainage on our website
Posted by Lincolnshire County Council at 21:40, Thursday 15 January 2026
-
Thank you for your report. We will investigate and make an update to this report within 14 days.
Posted by Lincolnshire County Council at 21:42, Thursday 15 January 2026
-
Great news, we’ve had a look at the issue and we have now passed to our Highways Officers for the team to assess what can be done to resolve the matter. We’ll let you know when the assessment has taken place.
State changed to: Investigating
Posted by Lincolnshire County Council at 12:29, Friday 16 January 2026
-
Progress! We’ve completed our investigation and works are now planned. Once we know when work is due to take place we will let you know.
State changed to: In progress
Posted by Lincolnshire County Council at 13:38, Tuesday 20 January 2026
-
We have an update. Our highways team have issued this work out to one of their delivery gangs. We’ll let you know when the job is complete.
State changed to: Action scheduled
Posted by Lincolnshire County Council at 10:26, Friday 6 February 2026
-
State changed to: In progress
Updated by Lincolnshire County Council at 07:43, Tuesday 10 February 2026
-
All done! The work’s finished and the issue is now resolved. Thank you for contacting us about this. Your report has meant that we can focus our effort where it’s needed most.
State changed to: Fixed
Posted by Lincolnshire County Council at 07:43, Tuesday 10 February 2026
-
State changed to: In progress
Updated by Lincolnshire County Council at 20:55, Monday 16 February 2026
Only the original reporter may leave updates. If you made the original report please log in to leave an update.