Fixed
High bridge Spalding
Reported via desktop in the Pothole on road/cycleway category anonymously at 17:17, Sunday 1 March 2026
Sent to Lincolnshire County Council less than a minute later. Council ref: 2882080.
Top layer of tarmac missing, cobbles below on view causing vehicles to swerve.
Updates
-
Thanks for letting us know about your issue with a pothole on the road or cycleway. We will look into this and let you know what we find within the next 14 days. You can find out more about potholes on our website
Posted by Lincolnshire County Council at 17:17, Sunday 1 March 2026
-
Progress! We’ve completed our investigation and works are now planned. Once we know when work is due to take place we will let you know.
State changed to: In progress
Posted by Lincolnshire County Council at 09:27, Monday 2 March 2026
-
We have an update. Our highways team have issued this work out to one of their delivery gangs. We’ll let you know when the job is complete.
State changed to: Action scheduled
Posted by Lincolnshire County Council at 09:03, Monday 9 March 2026
-
Very very deep pot hole on the bridge, as you turn left over the bridge you have to come really close to the side to avoid it. very dangerous
Posted anonymously at 11:53, Monday 16 March 2026
-
State changed to: In progress
Updated by Lincolnshire County Council at 18:48, Friday 19 June 2026
-
The work required to resolve this issue has now been completed. Thank you for contacting us about this. Your report has meant that we can focus our effort where it’s needed most.
State changed to: Fixed
Posted by Lincolnshire County Council at 23:52, Friday 19 June 2026
Only the original reporter may leave updates. If you made the original report please log in to leave an update.