Action scheduled
Outside the Row 1-4 flooding
Reported via desktop in the Standing water covering more than half the road category by Cllr D East at 20:10, Thursday 7 May 2026
Sent to Lincolnshire County Council less than a minute later. Council ref: 2890842.
Out of date updates, has flooding on this road been addressed?
Updates
-
Thanks for letting us know about your issue with standing water covering more than half the road. We will look into this and let you know what we find within the next 14 days. You can find out more about flooding and drainage on our website
Posted by Lincolnshire County Council at 20:10, Thursday 7 May 2026
-
Thank you for your report. We will investigate and make an update to this report within 14 days.
Posted by Lincolnshire County Council at 20:45, Thursday 7 May 2026
-
Just to let you know this issue has turned out to be more complicated than we first thought. We need to take this on for more investigation. We will let you know the situation as soon as we can. Thanks for bearing with us.
State changed to: Investigating
Posted by Lincolnshire County Council at 07:32, Monday 11 May 2026
-
Progress! We’ve completed our investigation and works are now planned. Once we know when work is due to take place we will let you know.
State changed to: In progress
Posted by Lincolnshire County Council at 11:14, Thursday 21 May 2026
-
We have an update. Our highways team have issued this work out to one of their delivery gangs. We’ll let you know when the job is complete.
State changed to: Action scheduled
Posted by Lincolnshire County Council at 10:27, Wednesday 17 June 2026
-
Can we please have this updated?
Posted by Cllr David East at 17:14, Tuesday 28 July 2026